狠狠97人人婷婷五月,99久久精品国产一区二区三区,国产日韩综合一区在线观看,精品久久亚洲一级α,五月激激激综合网色播

Tianjin zhongwang 220kV substation officially sent power

Time:2014-12-19

    On December 17, 2014, tianjin zhongwang 220kV substation was officially put into operation.As one of the key projects of tianjin electric power engineering, its operation will also become the first 220kV user substation in wuqing district.
   Zhongwang 220kV substation is located in the factory of tianjin zhongwang aluminum co., LTD., shangmatai town, wuqing district.The substation started construction on August 18, 2013. Through the hard work of the constructors of tianjin power transmission and transformation engineering company, the project was successfully completed on December 16, 2014 in a timely, quality and satisfactory way with 16 months to overcome such conditions as short construction period, heavy task, high requirements and complex construction conditions.
   At 19:00 on December 17th, as the equipment in the station started one by one, the whole substation was officially operated according to the predetermined plan.The person in charge of the main control room of the station reported that at present, all the equipment of the station is running normally.
   Tianjin zhongwang 220kV substation as the company's own investment and construction of the enterprise substation, its formal transmission will effectively solve the growing power demand in the plant, for the company's production equipment commissioning production to provide a strong power supply.


版權所有:天津忠旺鋁業(yè)有限公司 Copyright Tianjin Zhongwang Aluminium Co.,LTD. 2014 all reserved

津公網(wǎng)安備 12011402000938號

狠狠97人人婷婷五月,99久久精品国产一区二区三区,国产日韩综合一区在线观看,精品久久亚洲一级α,五月激激激综合网色播